Immediate Recommendations

To be completed by December 1 2018

     
    • Install 18 ring nets in 5 key canyons; adds between 90k-110k cubic yards of capacity
      • Cold Springs (debris basin capacity 13k cubic yards)

      • Hot Springs

      • San Ysidro (debris basin capacity 11k cubic yards)

      • Buena Vista

      • Romero (debris basin capacity 27k cubic yards)

    • Stage another 27 ring nets for 2019; adds a total of 250k-300k cubic yards of capacity
    • Final mapping of locations and permitting over next few weeks to make most impact in each Canyon, protecting areas without debris basins and supporting those areas with debris basins
    • Collaborating with Public Works, Planning and Development, USFS, private land owners
    • Could be temporary for 5 years, allowing for county to implement debris basin strategy
     